Sunbury Line Upgrade

The $1.8 billion Sunbury Line Upgrade has been delivered with new tracks now connecting the line to the Metro Tunnel’s western entrance in Kensington.

Work began on the Sunbury Line Upgrade in 2019 and included power and signalling upgrades, platform extensions and station accessibility improvements, and upgrades to train stabling at Sunbury, Calder Park and Watergardens. These enhancements were needed to take full advantage of the extra capacity created by the Metro Tunnel and for more modern trains to run on the Sunbury Line from 2025.

Once the Metro Tunnel is open people travelling on the Sunbury Line will have direct access to 5 new stations at Arden, Parkville, State Library, Town Hall and Anzac – improving access to employment, education and other opportunities across the city and in Melbourne’s booming north west.

The Sunbury Line Upgrade delivered:

  • Power upgrades, including building 5 new substations and upgrading 10 substations so bigger, more modern trains can run on the line
  • new High Capacity Signalling to enable more frequent services
  • extended platforms at 8 stations and raised platform boarding pads
  • expanded train stabling facilities at Sunbury, Calder Park and Watergardens
  • removal of the Gap Road level crossing in Sunbury, in partnership with the Level Crossing Removal Project.

Project timeline

2018

Project announcement

  • Site investigations begin

2019

Project commences

  • John Holland, CPB Contractors, AECOM and Metro Trains Melbourne awarded for the first package of works
  • Site investigations for the platform extensions and stabling upgrades start
  • Major works on the platform extensions and stabling begin

2020

Major construction and community consultation

  • Major track, power and platform upgrades completed
  • Community and stakeholder feedback received on design solution for Gap Road level crossing removal and substation design
  • Planning approval received for the Gap Road level crossing removal

2021-2023

Major construction

  • Sunbury Line and Gap Road Level Crossing removal works

2023

Project complete

  • New track connecting the Sunbury Line to the Metro Tunnel western entrance in Kensington
  • Landscaping and finishing works completed
Line map, showing station points and upgrades along the Sunbury Line.

Some Government images of the extensive works